mayor Stefan Hemmerling want to know exactly and invites the planner last in the municipal Council. Corona due to the as before, in the village community house meets in Wulfen, which stands remarkably well filled. It is the municipal Council of the project ideas and the use of renewable energies.

UKA Meißen, a company with around 600 employees, will be presented this evening in Wulfen is a “very complex project” in the wind fitness area Drosa/small double life. A project with multiple construction stages.

at Present, it was in the approval process

Currently, it says, is in Phase 1. Here, there are two wind turbines in the area of Drosa. Nico Less, the responsible project Manager, informed of the Construction. The construction had begun. He assume that the plants can go at the beginning of 2021 in operation.

In Phase 2 are for the single system reschedules required, it says. At present, you are transported to the procedure in the approval. His company, Nico Less, count in the first quarter of 2021 with all the necessary documents. The municipality had been involved, adds Stefan Hemmerling later, on demand of the MZ.

another wind Turbine, for the UKA “in the next few weeks”, as in the meeting, it is said, the application for a permit wants to make, is Phase 3. Add to that two additional plants in Phase 4 in the South part of the wind-suitability area.

“The area will change,” explains Nico Less in the municipal Council

Also, the company intends to submit as your project Manager announces in Wulfen, in a timely manner all documents. Thus, the local councils know now that a total of six wind turbines are planned. At present, a transformer substation, which is planned to go in the third quarter and in several stages which can be extended.

“The area will change,” explains Nico Less in the municipal Council, and announces that will reduce the number of plants. 27 plants are from 2005, four have already been built in 2002.

With about 240 meters – 160 meters hub height and a diameter of 160 meters for the wind Turbine are the newly planned facilities is twice as high as those that are there already, explained mayor Stefan Hemmerling of the MZ in the aftermath of the Council meeting. (mz)

This article was written by Sylke Hermann

*The contribution of “New plans: In the case of Drosa and small double life of six wind turbines” published by Central German newspaper. Contact with the executives here.

Central German newspaper