The jam-madness breaks out on Monday: Anything goes more in the direction of Garmisch-Partenkirchen. Why, above all, a site office and a half-sided block on the B2. The highway Department responded.
hours, motorists need on Monday for a track that you back normally within 30 minutes and less. Three hours from Eschenlohe to Garmisch-Partenkirchen. Four hours of Riegsee in the place – to name just a few examples. Traffic jam may be the Locals and also the guests in the usual way. What you will experience but on Monday in the early hours of the morning – in the rain mind you, and after the holidays -that will exceed your expectations. About hours are at a standstill. Mainly due to a construction site on the side of the road and the main street in Partenkirchen, which are closed to traffic on one side of the direction of the South.
Although had announced the Road administration because of the home and the Work. However, with this Chaos, no one had expected this. On Monday, the authority responded.
road building Department to plans to: be Working at night
it was Originally planned that the renovation work until Friday, 19. June, with the current control on the B2 run. “The current traffic situation, however, requires quick Action and a re-planning of the Construction process”, it is part of the Department. In the night on Tuesday is cancelled, therefore, the half-block and the B2 can be used from early in the Morning, again in both directions. Further milling under half-sided block be done – if necessary – on Tuesday evening from 20 clock.
If the weather conditions permit, will be installed in the new roadway in two nights. The authority is planning, the state road from Wednesday, 17. June, between 20 and Thursday, 18. To block June, 6 o’clock, half-sided. The second installation phase is scheduled in the night on Friday, and again between 20 and 6 PM.
Due to weather conditions: Work may be delayed
it was Originally intended, the Work in the brightness of the day. Thus, according to the Road administration, to reach a “significantly better quality”. For the installation of the new roadway, it must be sufficiently long to dry. Therefore, the authority cannot exclude, given the rainy weather, the installation of the surface moves again.
During the half-side blocking the traffic heading South will be diverted from the Farchanter gyro on the B 23 to the town hall square, the northbound traffic runs one lane on the B 2 to the site. The access roads to the adjacent land, emphasizes the building Department, are to be largely maintained. With short-term closures, however, is to be expected. Because of the one-way regulation on the B 2, the access from the South is the exit to the North. After the completion of the ceiling construction, the road markings will be in the following week applied.