In October 2019, has been renovated in the village Partenkirchen up to the town hall intersection, first complete the construction vehicles to back again. The reason the damage occurred soon again. Now the ceiling needs to be made again.
Garmisch-Partenkirchen – This should be the nightmare of every road Builder. You draw on the ceiling of a main road in a few days – and after a short time the first Set to burst again. It quickly becomes clear that Is not so.
On the part of Kirchner’s main through-road (Münchner Straße/Hauptstraße) is exactly what happens. Only in October 2019, the state Department had issued the order to leave the area from the roundabout to the town square with a new Tar surface evidence. The night site is still remembered by many. Now, the whole spectacle must be repeated: 1.5 inches top ceiling off, a new layer. Let’s go already on Monday, 15. June. Scheduled the repair for over a week until Friday at noon.
“was not Planned,” emphasises Nadine Hot from the State Department in Weilheim. “And it is annoying for all sides.” For the authority, because the site could not be completed, for the residents, because again, there is noise and Dirt, for the traffic participants, but also for the company, is allowed to perform the Work twice. But: “We want a performance that is in order,” says Hot significantly. Blame, you will not speak. The weather had beaten the building professionals in the last autumn, a trick, the Work significantly more difficult. Cold and wet it was. “Because some things always play together.” The bill conceded the professionals soon: The pavement of the national road 2 to burst in many Places. The company has yet to once answer. To a large extent, on their own expense. Hot, the head of the Department for the County, was not in the cards. Only so much: “The entire project does not need to be paid for it once.”
For the market community, this means in the coming week additional traffic problems. Affected both districts: Partenkirchen, directly through the construction site, Garmisch because of the redirection from the direction of North (Murnau). Because the traffic is still derived before the roundabout at the entrance – on the B23 (burgstrasse) to the town square and then back to the B2 to Mittenwald. In the direction of the North, vehicles will be directed over one lane at the construction site. “This traffic control will remain even at night,” notes Hot. Otherwise the restoration would not be realized reasonably. To get “the best possible quality, we need large areas with as little seams as possible. So the traffic can flow only one lane over.“
the choice of the time window, the authority of language closely with the construction company. “For June, we have the hope of better conditions,” says Hot. The Work should also be done, in principle, during the day between 7 and 18 o’clock, only in the exceptional case at night. After all, the managers were able to avoid the Whitsun holidays, the on Sunday, 14. June, ends. Specifically, it has not been taken but. Hot: “You always have to look, what capacity.” In this Corona-the year everything was anyway different. “It often comes out differently than you think.”
The refurbishment of ceilings on the further route from the town hall square to the southern End of the village stands this year on the Plan. The municipality works on the main road as we know, just a new channel to install. Thereafter, the state building authority on the series. “But in November, we’ll start with a new blanket.” This should be in 2021.
info for local residents
the access roads to The adjacent land, will be largely maintained. With short-term closures, however, is to be expected. But it is because of the one-way regulation on the B 2 in each case only one access road from the South and an exit to the North is possible.